How to plan user capacity per day on TFS'12 Scrum Template 2.0
问题 I want to specify the team capacity per user and per activity on TFS'12 Scrum Template 2.0, which may differ on every day on the sprint. As described in http://msdn.microsoft.com/en-us/library/ee191595.aspx I can set capacity per day of a person, like 7 hours for a sprint of 5 days. How can I specify a capacity like the one below? Day 1 : 7 hours Day 2 : 5 hours Day 3 : 9 hours Day 4 : 3 hours Day 5 : 6 hours Thanks. 回答1: As others have mentioned, the TFS capacity planning doesn't support