your project should define the version only in the parent (project) only once. And let all other modules have a parent relationship. This means you don't have a aggregation. You have a multimodule build instead.

Project  
|-pom.xml (version 0.1-SNAPSHOT)
|-DB  
| |-pom.xml (parent: ..)
|-Business  
| |-pom.xml (parent:..)

This will solve your problem (May be you can take a look here as an example).

For the multi module project, when it fails for child snapshot dependency try this release:clean release:prepare release:perform -DignoreSnapshots=true

Hope it helps.

I was able to succeed at doing this using Maven 3.3.9...but let me describe my case scenario:

I work with a Java framework called Liferay, where there is a tool called Service Builder that can build and deploy services using Maven with the exact structure as you described:

Service Layer
|-pom.xml (version 1.12.0-SNAPSHOT)
|-Service Portlet
| |-pom.xml (version 1.16.0-SNAPSHOT)<---   
|-Service                               | Artifact dependency
| |-pom.xml (version 1.5.0-SNAPSHOT)-----

As you can see, the portlet app module is built with the service being a dependency, which is a .jar file that packs interfaces among other things for the services to work.

By the way, I did this with my project using modules of different versions. I found an interesting article talking about this practice: Releasing modules of a multi-module project with independent version numbers. You can read the abstract to draw your own conclusions about if versioning modules is appropriate or not... but from my point of view, after reading the demands of the Client, it seems reasonable to me that versioning of modules should be a feature supported by Maven without being too painful to implement.

Running mvn release:prepare and mvn:perform inside the parent (Service Layer) was the way to go. Maven makes the release building and deployment in the following order: 1) parent pom 2) service dependency 3) service portlet.

Maven took care of the order, and that is nice...but the service dependency is built based on the portlet source code, with a goal being run in the parent project: mvn liferay:build-service...so the dependency is affected by the source code of the portlet app (sounds a little crazy). That was a tricky part in my case.

So how do we get the service dependency built and deployed for the service portlet to use it?

Well, the solution for this was using a configuration within the maven-release-plugin that allows Maven to run particular goals in the release:perform phase within any of the projects. What I did is adding this configuration in the maven-release-plugin declaration in the parent pom.xml (Service Layer):

<plugin>
  <groupId>org.apache.maven.plugins</groupId>
  <artifactId>maven-release-plugin</artifactId>
  <version>2.5.2</version>
  <configuration>
   <goals>clean liferay:build-service deploy</goals>
  </configuration>
</plugin>

And Maven was able to deploy the parent and each of the children modules with our preferred version numbers (you will be asked to input them).

Summarized answer and recommendation: try using the <goals> configuration and run mvn release:prepare and mvn release:perform at the parent level

Parent and modules should be deployed following the order.

I hope this inspires someone in a similar situation at least, after 5 years.