I'm trying to add timesheet entries against some specific task which is available in the MS Project Server 2013. I have ways of creating TASK in Project Server using REST endpoints, but could not find a way straight forward for the timesheet. I have gathered few details out of some scrutiny at my end:
To See the Complete Meta Data: http://>/PWA/_api/ProjectData/$metadata - You can get the field details, Where as I need to know in specific the Entity for TimeSheet. To See the Complete Time Sheet Period Available: http://>/PWA/_api/ProjectServer/TimeSheetPeriods - You can see all the available TimeSheet Periods.
I know TimeSheet stays as separate entity and doesn't belong to usual Project Entities.
My Query here to know in specific the Entity that is dealt for timesheet add & update. Please help me with endpoints including the save, publish and checkout!
回答1:
How are you adding the tasks? Http requests? Did you develop some app?
I tried a few ways to add actuals to timesheets already created using REST endpoints, via Postman, without success. It always responds with this error: "The security validation for this page is invalid.", I think I'm missing some headers.
This endpoints were as close as i got:
Submit Timesheet
POST - http://>/pwa/_api/ProjectServer/TimeSheetPeriods('periodid')/TimeSheet/submit(comment)Update Timesheet
POST - http://>/pwa/_api/ProjectServer/TimeSheetPeriods('periodid')/TimeSheet/update()
I saw this endpoints here.
Hope this helps!
来源:https://stackoverflow.com/questions/54485790/timesheet-entry-into-project-server-using-rest-api