How to export backlog items from scrum to agile template in TFS 2015

老子叫甜甜 提交于 2019-12-12 04:14:21

问题


I need a clarification on how to export backlog items from scrum process to agile process in TFS 2015.

The hierarchy is Epic --> feature --> task --> bug...... based on these backlog items need to be export from scrum and import to agile process template.


回答1:


You can use Excel to export and import the work items between Scrum and Agile.

Please follow below steps to do that:

  1. Create a Tree of work items query for the work items you want to export in Scrum project.
  2. Open the query in Visual Studio, Click Column Options to select which column you want to display/export, then select Open Query in Microsoft Excel.
  3. Create a same hierarchy for the work items as the Scrum project in your Agile project, then create a Tree of work items query.
  4. Open the Agile query in Visual Studio, Click Column Options to select same columns as the Scrum query (Basically select the columns you want to import ), then select Open Query in Microsoft Excel.
  5. Copy the work items from Scrum to Agile in excel (Copy the contents from step2 to step4, please make sure that they have same columns for both query, you may need to edit some of columns to match the Agile values, as Scrum and Agile have different process workflow)
  6. Just click the 'Publish' to import the work items to Agile once complete the modification.



来源:https://stackoverflow.com/questions/44481027/how-to-export-backlog-items-from-scrum-to-agile-template-in-tfs-2015

标签
易学教程内所有资源均来自网络或用户发布的内容,如有违反法律规定的内容欢迎反馈
该文章没有解决你所遇到的问题?点击提问,说说你的问题,让更多的人一起探讨吧!