How to setup activity automatically for a view?

前端 未结 2 814
南方客
南方客 2021-01-14 05:33

In our build , we use to delete our view and create new view before build.

It was working without any issue in base clearcase.

But in UCM we face issues whil

相关标签:
2条回答
  • 2021-01-14 06:20

    @Samselvaprabu , agreeing with VonC on other things and that activities are,at best, logical groupings of code/development tasks. For example 5 source code + 1 property files for resolving a QA defect.

    Though when you ask how many activities ? there is no specific guideline which IBM provides (AFAIK) on this, but in my experience

    1. A typical activity may not have too few, meaning 1,2 files or too many (say 15+) files.
    2. An activity naming convention (though inconsistent when manual) would help. For example username_ShortDescreption/DefectID_date might help in organizing, sorting of activites when the need arises. And trust me, it will.
    3. Obsoleting activities based on some criteria such as age (more than 1 month) is good for housekeeping.
    4. An activity per build ?? - I would say this is subjective to how many times you build, how many artifacts go per build , how many view/developers you have and so on. You could have a build<>activity relationship which is 1<>n or n<>1 which is completely case-specific to your environment. That's the beauty and also the curse of UCM.

    These suggestions are not exactly would you asked for but I feel this a a good time to give them as you are just starting with this complex, messy world called UCM :)

    0 讨论(0)
  • 2021-01-14 06:22

    Use cleartool setact to set your activity.

    setact/ivity [ –c/omment comment | –cfi/le pname | –cq/uery | –nc/omment ]
    [ –vie/w view-tag ] { –none | activity-selector } 
    

    You might need to unset the current activity first from your view:

    Cleared current activity from view java_int.

    cleartool setactivity -none
    

    Then, Set an activity to be the current activity.

    cleartool setactivity create_directories
    Set activity "create_directories" in view "webo_integ".
    

    See "Setting UCM activities" for more:

    You can set only one activity per view at a time, and all checkouts in your view are associated with the currently set activity until you unset the activity or set another one.

    cleartool setact -view <myViewTag> <anActiviyName>
    

    (-view set before the activity name)


    Note that if you are changing the activity while you have pending checkouts, you will have a warning.

    You usually associate activities to a development task instead of a build number.
    Since you don't version what you are building (the executables), you don't have to make a new activity per build.