Is there a way to configure MS Project 2013 so that it displays in a resource column (eg, resource initials) of the Gantt Chart view of summary tasks the UNION of all resou
Those resource fields exist at the summary level because you can directly assign resources to a summary task, so you can't use those fields for this purpose. However, here's a macro that aggregates the names of the resources assigned to the subtasks. The results are put in Text1 at the summary level. You can then modify the Gantt chart bar styles to show that text field.
Sub RollupResourceNames()
Dim tsk As Task
Dim list As String
Dim key As Variant
For Each tsk In ActiveProject.Tasks
If tsk.Summary Then
Dim col As New Collection
Set col = GetChildResourceAssignments(tsk)
list = vbNullString
For Each key In col
list = list & ", " & key
Next
If Len(list) > 2 Then
list = Mid$(list, 3)
End If
tsk.Text1 = list
End If
Next tsk
End Sub
Function GetChildResourceAssignments(parent As Task) As Collection
Dim col As New Collection
Dim child As Task
Dim asn As Assignment
For Each child In parent.OutlineChildren
If child.Summary Then
Dim col2 As New Collection
Set col2 = GetChildResourceAssignments(child)
Dim key As Variant
For Each key In col2
col.Add key, key
Next key
End If
For Each asn In child.Assignments
On Error Resume Next
col.Add asn.Resource.Name, asn.Resource.Name
On Error GoTo 0
Next asn
Next child
Set GetChildResourceAssignments = col