How can I calculate the number of work days between two dates in SQL Server?

Monday to Friday and it must be T-SQL.

24条回答
  •  攒了一身酷
    2020-11-22 01:35

    All Credit to Bogdan Maxim & Peter Mortensen. This is their post, I just added holidays to the function (This assumes you have a table "tblHolidays" with a datetime field "HolDate".

    --Changing current database to the Master database allows function to be shared by everyone.
    USE MASTER
    GO
    --If the function already exists, drop it.
    IF EXISTS
    (
        SELECT *
        FROM dbo.SYSOBJECTS
        WHERE ID = OBJECT_ID(N'[dbo].[fn_WorkDays]')
        AND XType IN (N'FN', N'IF', N'TF')
    )
    
    DROP FUNCTION [dbo].[fn_WorkDays]
    GO
     CREATE FUNCTION dbo.fn_WorkDays
    --Presets
    --Define the input parameters (OK if reversed by mistake).
    (
        @StartDate DATETIME,
        @EndDate   DATETIME = NULL --@EndDate replaced by @StartDate when DEFAULTed
    )
    
    --Define the output data type.
    RETURNS INT
    
    AS
    --Calculate the RETURN of the function.
    BEGIN
        --Declare local variables
        --Temporarily holds @EndDate during date reversal.
        DECLARE @Swap DATETIME
    
        --If the Start Date is null, return a NULL and exit.
        IF @StartDate IS NULL
            RETURN NULL
    
        --If the End Date is null, populate with Start Date value so will have two dates (required by DATEDIFF below).
        IF @EndDate IS NULL
            SELECT @EndDate = @StartDate
    
        --Strip the time element from both dates (just to be safe) by converting to whole days and back to a date.
        --Usually faster than CONVERT.
        --0 is a date (01/01/1900 00:00:00.000)
        SELECT @StartDate = DATEADD(dd,DATEDIFF(dd,0,@StartDate), 0),
                @EndDate   = DATEADD(dd,DATEDIFF(dd,0,@EndDate)  , 0)
    
        --If the inputs are in the wrong order, reverse them.
        IF @StartDate > @EndDate
            SELECT @Swap      = @EndDate,
                   @EndDate   = @StartDate,
                   @StartDate = @Swap
    
        --Calculate and return the number of workdays using the input parameters.
        --This is the meat of the function.
        --This is really just one formula with a couple of parts that are listed on separate lines for documentation purposes.
        RETURN (
            SELECT
            --Start with total number of days including weekends
            (DATEDIFF(dd,@StartDate, @EndDate)+1)
            --Subtact 2 days for each full weekend
            -(DATEDIFF(wk,@StartDate, @EndDate)*2)
            --If StartDate is a Sunday, Subtract 1
            -(CASE WHEN DATENAME(dw, @StartDate) = 'Sunday'
                THEN 1
                ELSE 0
            END)
            --If EndDate is a Saturday, Subtract 1
            -(CASE WHEN DATENAME(dw, @EndDate) = 'Saturday'
                THEN 1
                ELSE 0
            END)
            --Subtract all holidays
            -(Select Count(*) from [DB04\DB04].[Gateway].[dbo].[tblHolidays]
              where  [HolDate] between @StartDate and @EndDate )
            )
        END  
    GO
    -- Test Script
    /*
    declare @EndDate datetime= dateadd(m,2,getdate())
    print @EndDate
    select  [Master].[dbo].[fn_WorkDays] (getdate(), @EndDate)
    */
    